Power





REVAMPING OF INDUSTRIAL SERVICES CARDON - RSI PROJECT

Tecnoconsult as the consortium leader, performed this relevant project for the Cardon Refinery, which scope included the design and construction for the new steam generation facilities with the installation of 5 new boilers of 155 ton/hour each, and all associated equipment, two new group of steam turbine and four electrical generator of 13 MW capacity each, the new electrical distribution system in 13, 8 Kv with 11 electrical substations. The project also included new facilities for treatment of refrigerated water, air compressor and air distribution network.

Location:

Falcon State, Venezuela

Client:

PDVSA

Scope:

Engineering, Procurement and Construction Management