Industrial





LOMA DE NIQUEL PLANT

Tecnoconsult was contracted to execute the detail engineering, procurement and construction management of this nickel mine processing plant with production capacity of 1.2 million tons of ore with an average nickel content of 1.44%. The project included belt conveyor; electrical furnace, 230- 34,5 KV substation, 230 KV transmission lines; earth movement and dam construction, and service facilities such as roadways, potable water supply, industrial and fire fighting water.

Location:

Aragua and Miranda States, Venezuela

Client:

Minera Loma de Niquel-ANGLO AMERICAN

Scope:

Engineering, Procurement, Construction Management