JOSE OLEFIN COMPLEX

Tecnoconsult, Fluor and Snamprogetti, contracted with Mobil/Pequiven to complete front-end engineering and capital cost estimating services for the Jose Petrochemical Complex. Major petrochemical process units include Ethylene 750,000 metric tons per annum (MTA); Linear Low-density Polyethylene (LLDPE)-300,000 MTA; Low-density Polyethylene (LDPE)-200,000 MTA; and Ethylene Glycol 400,000 MTA.

The José Olefin Complex received an Independent Project Analysis “Best in Class” rating of 4.25. Instrumental in assigning the rating was the fact, cited by the IPA, that the Join Venture brought the project through front-end loading (FEL) in 11 months compared to the industry average of 16 months. The José Olefin Project also incorporated 11 of 12 possible Value Improving Practices (92 percent). Each practice enhanced the quality of project definition.

Location:

Jose, Anzoategui State,Venezuela

Client:

Mobil/Pequiven

Scope:

FEL, Cost Estimating